Timeline



January 1967

Establishment of the first
eucalyptus plantations

April 1972

Foundation of Aracruz Celulose

September 1978

Start-up of the first
production unit (mill "A")

January 1985

Start-up of Portocel

February 1991

Start-up of the second production
unit (mill "B")

May 1992

Launch of ADR Level 3 shares on the New York Stock Exchange

January 1993

ISO 9002 certification
 

July 1995

ISO 9001 certification for all activities

April 1996

ISO 9002 certification for the electro-chemical plant

March 1997

Entry into the solid wood products industry (Lyptus)

August 1999

Beginning of Aracruz Produtos de Madeira operations

October 1999

ISO 14001 certification

October 2000

Aracruz acquires a 45% stake in Veracel pulp mill
project

February 2001

Start-up of Fiberline C feasibility study

November 2001

Acquisition of Mondi's stake (28%) by VCP

August 2002

Start-up of Fiberline C

July 2003

Aracruz acquires Riocell

May 2005

Start-up of Veracel

September 2005

Veracel inauguration

September 2008

Laying of the cornerstone for Guaíba expansion project